Provision of multiple survey crews to work under direction from the Survey Manager (Leighton). Surveying within a live rail environment for the construction of a new station facility, with the roof supported on curving steel trusses mounted on circular steel columns. The final stage of the works required the setting out for approximately 70,000 cleats on curved steel purlins, to receive the individually designed roof sheets: software routines were developed to allow for the identification of the required positions, allowing for the as-built location of the purlins.